Thickness dominates
A slab at 6 in needs 50% more concrete than the same slab at 4 in — depth is a linear multiplier on volume.
concrete calculator
Estimate how much concrete you need for a slab, footing, wall, column, stairs, or curb. Enter the shape and dimensions, and this calculator returns the volume in cubic yards plus the number of 60-lb and 80-lb bags — with a waste allowance you control and every step of the math shown.
Quick answer
A 10×10 ft slab at 4 in needs ~1.23 cu yd of concrete before waste — order ~1.36 cu yd (≈ 62 bags of 80-lb) with 10% waste.
Enter your project
Start with a preset
Live result
1.36 cubic yards
What you order
The model, unpacked
10 × 10 ft slab at 4 in
Concrete volume
1.23 cu yd
Waste allowance (10%)
+0.12 cu yd
Order this much (ready-mix)
1.36 cu yd
Or 80-lb bags
62 bags
Or 60-lb bags
82 bags
You may also need
Planning a full project? Most jobs use more than one material. You will often pair gravel, paver base and sand with concrete on the same site.
Interpret the output
A trustworthy estimate explains the levers behind the number. These are the factors that change how much you need to order.
A slab at 6 in needs 50% more concrete than the same slab at 4 in — depth is a linear multiplier on volume.
Round columns use πr², so a 12-in column holds far less concrete than a 12-in-square form of the same height.
Under about 1 cubic yard, bags are practical. Above it, ready-mix is cheaper per yard and avoids mixing 60+ bags by hand.
FAQ
Straight answers about quantities, conversions, and how much to order — no lead-gen fog.
45 — each 80-lb bag yields about 0.60 cu ft, and 27 ÷ 0.60 = 45. A 60-lb bag yields about 0.45 cu ft, so 60 per cubic yard.